New Port of Veracruz

  • Work Progress #3

    20 August, 2018

    Clients Hutchison Ports ICAVE attended a cocktail party where the status of the New Port of Veracruz was informed. The work of the new Terminal ICAVE continues to evolve favorably, planning that the major equipment will grow 40% in the first phase, with 7 container ship cranes in the dock, including two recently acquired. It […]

  • Work Progress #2

    30 June, 2018

    The New Port of Veracruz is a reality On May 25th, our clients distinguished us with their visit and were able to confirm the arrival of the two new gantry cranes, with which their operations will be handled at the HUTCHISON PORTS ICAVE facilities in the new port of Veracruz. The first vessel is expected […]

  • Work progress #1

    22 May, 2018

    Work progress in the new Port of Veracruz. To this  date, 11.8 million cubic meters have been dredged, which corresponds to 94% of progress. The 42 ha of the ICAVE’s lands, corresponding to phase 1, are 100% filled. Dredging works are set  to finish 60 days before the scheduled time. The works of the dock […]

Hutchison Ports in Mexico